A heat pump or solar claim stalls on paperwork, not on the installation: the Declaration of Works needs three signatures, the BER certificate comes from someone else, and SEAI pays nothing until every item is uploaded. This is the full set, in the order it matters, with the party responsible for each.
The deadline that catches people
You have eight months from the grant offer to have the works done, the post-works BER published and the signed paperwork back with SEAI. Payment then takes 4–6 weeks — longer if the home is inspected.
Miss the window and the claim is lost, not delayed.
What you submit after the works
| Document | Whose | Notes |
|---|---|---|
| Declaration of Works | Homeowner | Signed by the homeowner, the BER assessor and the registered contractor |
| Designer Installer form / Heating Design Sheet | Contractor | Heat loss and system design; supplied by the contractor |
| Ecodesign data sheet | Contractor | The unit's declared performance data |
| Request for Payment form | Homeowner | Arrives with the letter of offer; must match the bank account |
| Post-works BER certificate | BER assessor | Must be published by a registered SEAI assessor before drawdown |
| Tax Clearance Certificate | Homeowner | Only where grant payments exceed €10,000 in a calendar year |
| Safety file | Contractor | Handed to the homeowner; keep a copy for inspection |
| Technical Assessment or Self-Declaration | BER assessor | Pre-2007 homes without a valid BER at Heat Loss Indicator ≤ 2.3 |
Grant values change with dwelling type and system; this page is about the documentation, not the amount. Figures and process were read from SEAI's heat pump grant page on 5 November 2026.
Same shape, one extra certificate
| Document | Whose | Notes |
|---|---|---|
| Declaration of Works | Homeowner | Signed by the homeowner, the BER assessor and the registered contractor |
| Inspection, Test and Commissioning Certificate | Contractor | Completed and signed after commissioning |
| Safe Electric (RECI) certificate | Contractor | The electrical completion certificate |
| Request for Payment form | Homeowner | Arrives with the letter of offer |
| Post-works BER certificate | BER assessor | Published before drawdown |
| Tax Clearance Certificate | Homeowner | Only where payments exceed €10,000 in a calendar year |
| Safety file | Contractor | Handed to the homeowner |
Read from the SEAI Solar PV Scheme application guide, October 2026. Requirements can change: check the current guide before you rely on this page for a live claim.
Because three people have to sign one form
The installer is the only party who sees the whole claim, and the only one chasing a homeowner for a signature and an assessor for a certificate at the same time — usually while on a roof somewhere else.
Grant Pack tracks one job at a time: what is required, whose it is, what is still missing, and what the pack looks like when it is complete. It produces a pack sheet with the document index and the signature block, and it says on its face that it is a record, not a submission.
Installed on your own server
Install
€2,900 once. One container, one volume, your data on your machine or your IT provider's. No per-job fee, no commission.
Care
€780 a year. Checklist updates when SEAI changes a form, verified backups, patches, two support hours a month.
There is no licence key and no lock-out: if you stop paying, the tool keeps working and the data is still yours.
What installers ask
Is this a replacement for my own records?
No. It is the checklist and the pack sheet; your contracts, invoices and safety file remain yours.
Does it submit to SEAI?
No. It collects and indexes evidence. The claim is still made by the homeowner or the contractor through SEAI's own system.
What if SEAI changes a form?
The checklist is data, not code: it is updated and pushed to installations as part of care. That is the main reason to pay for care rather than host a copy.
How long does it take to set up?
An afternoon, including a test job from your last completed claim.